Technical information:
16 solar panels, modules Conergy S190
1 inverter conergy Vision IPG3000
3000Wc, 24 m² roof
Company who did the installation :
SARL SRCT Systèmes Solaires
Commandaire
63490 Usson
tél 04 73 71 98 98
www.systemessolaires.fr
The installation of solar panels have been done during the last week of June 2008. In August, the inverter has been installed by the electricien of the company. The end of September, the connection branch of the Electricity Company (ERDF) came to connect us to the grid, and, finally, the last work for the connection was done on the 30th of September. In all, it took 3 months to have the panels installed and connected.
|
The costs
Installation and materials (without VAT):
Price for all the administrative work:
VAT 5,5 %
Connection to the grid by ERDF
Total
|
19.236,00 euro
500,00 euro
1084,48 euro
575,46 euro
21.395,94 euro |
and financial incentives
Subsidy from the Region Auvergne
Deduction on Taxes |
1500 euro
not yet
|
|
The production
We started to produce on the 30th of Septembre 2008. There were days that we were producting up to 12 kW, and there were those very clouded days when we were not producing at all.
In this part of the webpage you will find a table with three montly productions figures, but we still need some more production months before we can give those.
|